Building bridges during major A1 upgrade, with our propping expertise

allerdene-bridge-584x584-3

Project Overview

Location
Sector
Application
Products

When it came to installing a new bridge as part of a major infrastructure upgrade, temporary works were a critical element given the poor ground conditions on site. Costain turned to us for our expertise.

The challenge

The bridge formed part of a major highway infrastructure upgrade designed to increase network capacity and support growing traffic demand. The scheme included carriageway improvements and the replacement of an existing bridge crossing over a key rail corridor.

The new bridge structure consisted of 16 central girders installed as braced pairs, comprising more than 3,000 tonnes of structural steel and decking. Understandably, the assembly and installation of the bridge presented project teams with a considerable logistical challenge, requiring a bespoke series of temporary works.

Ben Adcock, Lead Temporary Works Co-ordinator at Costain, principal contractor on the project, said:

“Due to the poor ground conditions experienced on site, the geotechnical team anticipated significant movement could occur at the back-span embankments and abutments during construction. As a result, we were unable to land the new bridge deck directly onto the new abutments, as the bridge bearings would not have been able to accommodate the anticipated movement and loads.

“Temporary works therefore proved critical to maintaining the programme. We needed a temporary propping and trestle scheme that would provide additional support to the back-span beams of the bridge deck during the initial installation phase, before loads could be gradually transferred to the permanent abutments.”

Supporting a major infrastructure upgrade

The bridge formed part of a major highway infrastructure programme designed to increase capacity and improve traffic flow along a busy transport corridor.

Working with a complex structure

The new bridge structure consisted of 16 central girders, installed as braced pairs, comprising over 3,000 tonnes of structural steel and decking.

Providing a logistical challenge

Understandably, the assembly and installation of the bridge presented project teams with a considerable logistical challenge, requiring a bespoke series of temporary works.

“We turned to MH International for the temporary works aspect of the project, as it’s widely known that propping is an area they really excel in. We knew that MH International and its wider teams could be relied upon to deliver a good service at the right time.”

Ben Adcock
Costain
Important technical notice

This project was completed by MH International’s parent company using shared personnel, under an intra group informal licence

Related news and projects

Contact Phone Number

Give us a call

For all project specific design and technical enquiries, please contact your local service team.

Send us an email

If you want to talk to us about your project, send us an email and a brief outline of how we can help and we’ll be in touch.

[email protected]

Get updates
on our latest news,
solutions and projects